HVAC Works

Glasgow

PROJECT DURATION: 8 Weeks

PROJECT VALUE: £300K+

Project Details

Design and install new HVAC system, allowing the gas boiler to be removed to align with client’s decarbonisation programme.

C&S carried out a wide scope of works including:

  • Removal of gas boilers/current heating system/chiller unit from roof/gas meters
  • Supply and install of new Daikin VRV 4 and flat pack air handling unit with heat recovery
  • Crane lift old and new units to roof
  • Supply of transition ducting and air flow ducting
  • Metal containment installation
  • Electrical installation
  • Connect pipework and wiring
  • Balancing full system
  • Vac out and commission system