HVAC Works

BOS Paisly

PROJECT DURATION: 8 Weeks

PROJECT VALUE: £260K
Project Details
Replace the complete heating and cooling system with a new Daikin VRV 4 and Altherma systems, allowing the gas boilers to be removed. Existing AHU to be removed and new installed which will need to be built in situ due to limited space. New VRV replaced on roof space (crane required).
C&S carried out a wide scope of works including:
- Removal of gas boilers/current heating system/chiller unit from roof/gas meters
- Supply and install of new Daikin VRV 4 on lower ground/ground floor/staff room and flat pack
air handling unit with heat recovery - Crane lift old units off roof and crane lift new VRV units onto roof
- Supply of transition ducting and air flow ducting to upper and lower banking hall
- Metal containment installation
- Electrical installation
- Connect pipework and wiring at condenser
- Air flow ducting commissioning
- Vac out and commission system