External Fabric Works

West Graham Street, Glasgow

PROJECT DURATION: 30 Weeks

PROJECT VALUE: £585K
Project Details
As part of the overall works, our team carried out extensive external fabric repairs to restore and protect the building’s structure.
C&S carried out a wide scope of works including:
- Erection of full height access scaffold to full building perimeter to facilitate works.
- Removal of localised brick courses to the head of window and door positions and insertion of
pre formed cavity trays and weep vents. - Removal of brickwork at parapet level to insert pre formed parapet trays.
- Removal of guttering system and redesign.
- New coping and flashing detailing to head of parapet upstand.
- Isolated roof works.
- Attic void works.