Our projects

Fire Prevention Works

Muirhouse, St.Augustines, St. Brendan’s Primary & Cardinal Newman Secondary School

PROJECT DURATION: 4 Weeks

PROJECT VALUE: £800k+

Project Details

C&S were appointed main contractor to rectify breaches found within fire risk assessments to schools for a local authority. On this project we carried out multiple fire-stopping works. These measures were essential for enhancing the fire resistance of the structure and enabling safe evacuation in the event of a fire.
The works were completed across the ground, first, second, and third floors.

C&S carried out a variety of works including:

  • Disconnection and removal of M&E Services
  • Removal of suspended ceilings
  • Asbestos removal works
  • Installation new fire blankets
  • Passive fire works
  • Encapsulation of steel beams
  • Reinstatement of M&E
  • New ceilings